See how our district is growing and improving!
This page is a resource for the community to follow along with our big facilities projects!
⬇️ CURRENT ONGOING UPDATES ⬇️
MISEC Brite / NorthStar Solar Panels
Project renderings - construction has not yet commenced.

Complete
Scope drawings completed
Interconnection
applications approved
NorthStar visits in progress
Project approved by Consumers for construction
In Progress
PE stamp drawings are being completed and will go to the state shortly
An updated schedule, including install, will be provided
Equipment needed is in storage with the EPC contractor and ready to go when the project is approved
Planning for provision of student learning opportunities throughout the project such as viewing the environmental review process. This is being done in coordination with NorthStar and Consumers Energy to build real-world career and work experiences for our students at various grade levels.
We are conducting bi-weekly meetings with NorthStar representatives
Walk-throughs of the elementary and jr/sr high exterior areas are going on as we prepare
Future
Construction start Spring 2025
Project completion estimated early August 2025
2024 Bond Proposal
Check out the Bond Updates page for a full breakdown of the ongoing process and to see progress pictures!

COMING SOON:
Multi-Phase Grant Project: Cultivating Comets' Mental, Physical and Social-Emotional Wellbeing by Growing Their Talents, Leadership and School Pride.
Over the past decade, we have made significant advancements in academic and agricultural curriculum, programming and offerings. Now, we are turning renewed attention to the arts and athletics, ensuring that our students have access to well-rounded experiences that meet their unique interests, build leadership skills and strong relationships and prepare them for lifelong success.
⬇️ COMPLETED PROJECTS ⬇️
Listed below are only a few of the most recent completed projects to improve facilities at Coleman Community Schools.