We did it!
We are thrilled to announce that progress has officially begun on the Jr/Sr High Bond process!
Thank you to our community for helping us make it happen!
Please use this bond webpage as a resource to access all updates and information on the completion of projects, current items in progress, and future projects coming up on our schedule.
![progress bar](https://cmsv2-assets.apptegy.net/uploads/5045/file/4190400/4dafc509-072f-4d9d-a9cc-d1713342e49b.png)
January 2025
Design Kick-Off Meeting with Wolgast & IDI
February 2025
The first set of schematics are being drafted
Reviewing number of spaces and square footage of each at the Jr/Sr High
Setting up meeting dates with CEA to discuss calendar for the 2025-2026 and 2026-2027 school years and its impact to the project
IDI and Wolgast are conducting site visits
Finalizing the bond website page and getting information to the community in Comet News, at community organization meetings, and in other ways
Creating a Shared Drive of all ideas and communications
Contracts coming to us from IDI and Wolgast
Visits to locations with recent updates
Feb - Summer 2025
Finalize sale of bonds
Ongoing biweekly meetings with construction management team and architect
July - Aug 2025
Design Development Drawings anticipated to be completed
Abatement testing
Aug - Sept 2025
Final Construction Documents go out to bid
Dec 2025 - May 2026
Abatement testing
Staff begins packing up classrooms in preparation for Summer 2026 projects
May - Sept 2026
Potential abatement testing may start during Spring Break 2026
Jr/Sr High construction projects to begin
Projects anticipated to be completed September 2026!
Bond construction projects include:
![bond plan](https://cmsv2-assets.apptegy.net/uploads/5045/file/3496781/aa7d58b0-2d3f-4bab-bd5b-93e430e46c12.png)
Project Scope Renderings
![library](https://cmsv2-assets.apptegy.net/uploads/5045/file/3685229/1538b975-62e3-4d7f-8874-ef2c0f67ff26.jpeg)
Current Media Center - No walls, open to hallway
![revised media center](https://cmsv2-assets.apptegy.net/uploads/5045/file/3685223/b71d8c68-02b7-48ae-a5d0-5a2852dc5110.png)
Proposed Media Center - Walled in, separated from hall
![nancy](https://cmsv2-assets.apptegy.net/uploads/5045/file/4248200/5a31fb48-4d40-4ee9-858c-bc9fdc0e4b66.png)
Mrs. Robison's Current Classroom
![steve](https://cmsv2-assets.apptegy.net/uploads/5045/file/4248192/206025af-7bee-4acc-aa29-147909ab039c.png)
Mr. Fox's Current Classroom
![classroom 1](https://cmsv2-assets.apptegy.net/uploads/5045/file/3685362/94c0a2a4-5b99-46c3-b3ba-d59ed6ffabc9.png)
Proposed Classroom Space - Efficient, squared-off
![hallway](https://cmsv2-assets.apptegy.net/uploads/5045/file/3689019/9cdf6478-f22f-407a-b8e8-de655ecc6d43.png)
Current Hallway/Lockers - Open to media center
![hallway](https://cmsv2-assets.apptegy.net/uploads/5045/file/3689026/92951948-d644-4493-9336-a884e6f5a07d.png)
Proposed Hallway/Lockers - Separate from media center
![current hallway](https://cmsv2-assets.apptegy.net/uploads/5045/file/3689090/cdc315b0-5df2-47e4-873d-f8ba18b6d55b.png)
Current Science Lab
![science lab](https://cmsv2-assets.apptegy.net/uploads/5045/file/3685345/2d299096-d8e5-42cc-bc85-8425eb78b61f.png)
Proposed Science Lab - working sinks/burners at stations